Soil Nail and Shotcrete Wall
Middletown, PA
JG was instrumental in developing the soil nail and shotcrete wall concept required to retain the earth from a new roadway embankment at an existing Facility in Middletown, Pennsylvania. JG constructed a 500-foot long, 10,500 square-foot soil nail and shotcrete wall in order to re-align a service road at the facility. The wall averaged 21 feet in height, with a maximum height of approximately 30 feet. JG installed 400 soil nails and placed over 700 cubic yards of shotcrete. After the structural shotcrete was placed, JG installed an architectural finish.
What Our Clients Say
Hear directly from those who’ve experienced the JG difference firsthand.